Syllabus: GS-III & V: Infrastructure
Why in the news?
The Ministry of Road Transport & Highways (MoRTH) has decided to impose penalties on contractors for accidents occurring on Build-Operate-Transfer (BOT) highway stretches — a significant step toward enhancing accountability. However, in the Northeast region, where highway construction and maintenance delays are chronic, the impact of such measures remains uncertain.
Current Situation in the Northeast
- Between 2014 and now, 74 out of 576 delayed national highway projects in India are in the Northeast.
- This includes 17 in Assam, 8 in Sikkim, 7 each in Arunachal Pradesh and Mizoram, 6 in Nagaland, and 4 each in Tripura and Meghalaya.
- National highways, though forming only 2% of India’s road network, account for over 35% of road-accident deaths, reflecting severe safety gaps.
- The region’s highways are frequently damaged by floods, landslides, erosion, and heavy rainfall, leading to weeks of traffic disruption and isolation of remote districts.

Key Issues
- Delays in Project Completion:
- Factors such as land acquisition hurdles, utility shifting, law-and-order problems, financial distress of contractors, and natural disasters have prolonged timelines.
- Force majeure events, including COVID-19, added to cost overruns and execution delays.
- Factors such as land acquisition hurdles, utility shifting, law-and-order problems, financial distress of contractors, and natural disasters have prolonged timelines.
- Maintenance Neglect:
- Even completed stretches face poor maintenance, with damaged pavements, unmarked diversions, and blocked drains, raising the risk of accidents.
- Post-disaster repairs are sluggish, showing lack of coordination among implementing agencies.
- Even completed stretches face poor maintenance, with damaged pavements, unmarked diversions, and blocked drains, raising the risk of accidents.
- Limited Accountability:
- The new MoRTH penalty clause applies only after project completion, making it difficult to fix responsibility for accidents during the construction phase.
- Under BOT norms, contractors are bound to maintain highways for 15–20 years, but penalties can be imposed only once these projects are operational.
- The new MoRTH penalty clause applies only after project completion, making it difficult to fix responsibility for accidents during the construction phase.
- Safety Infrastructure Gaps:
- Abrupt diversions, poor signage, and inadequate lighting make under-construction highways extremely hazardous for commuters.
- Abrupt diversions, poor signage, and inadequate lighting make under-construction highways extremely hazardous for commuters.
Policy and Accountability Measures
- Penalty Mechanism: If more than one accident occurs on a completed BOT stretch within a year, contractors face a penalty of ₹25 lakh, rising to ₹50 lakh for repeated negligence.
- Black-Spot Identification: MoRTH’s national programme identifies and rectifies accident-prone stretches through engineering redesign and safety audits.
- Act East Policy: Enhancing road connectivity in the Northeast remains central to India’s strategic outreach to Southeast Asia, making timely completion of highway projects a geopolitical as well as economic priority.
What Needs to Be Done?
- Strengthen Monitoring: Introduce real-time dashboards and independent third-party audits for ongoing and completed projects.
- Expedite Execution: Resolve bottlenecks in land acquisition, clearances, and contractor financing to ensure timely completion.
- Ensure Robust Maintenance:
- Conduct periodic inspections and enforce performance-based maintenance contracts.
- Create rapid-response teams for post-disaster road repairs.
- Conduct periodic inspections and enforce performance-based maintenance contracts.
- Enhance Safety Engineering:
- Mandate proper signage, lane markings, and slope protection in hilly terrain.
- Use geo-textiles and slope stabilisation technologies to minimise erosion.
- Mandate proper signage, lane markings, and slope protection in hilly terrain.
- Community Engagement: Empower local monitoring committees to report hazards and monitor contractor performance.
Exam Hook – Key Takeaways
- The Northeast’s highway network is crucial not only for connectivity but also for strategic and economic integration.
- While MoRTH’s penalty clause enhances accountability, it must be supported by timely execution, maintenance funding, and safety monitoring.
- Sustainable highway infrastructure requires a shift from reactive repair to preventive maintenance and climate-resilient engineering.
Mains Question
“Analyse the challenges of highway construction and maintenance in India’s Northeast region. Suggest institutional and engineering measures to ensure safe and timely completion.”
One-line wrap:
In the Northeast, highways are more than roads — they are lifelines that demand not just construction, but care, accountability, and resilience.
Share This Story, Choose Your Platform!
Start Yours at Ajmal IAS – with Mentorship StrategyDisciplineClarityResults that Drives Success
Your dream deserves this moment — begin it here.


