On 23 November 2026, 69 former bureaucrats urged the Union Environment Ministry to scrap the proposed 1,750-megawatt Demwe Lower Hydroelectric Project on the Lohit River in Arunachal Pradesh, citing threats to forests, endangered wildlife and indigenous communities.

About the Project

  • Location: It is situated on the Lohit River in Arunachal Pradesh, covering areas of Lohit and Anjaw districts.
  • Developer: Initially developed by Athena Demwe Power Limited, the project is now associated with Greenko Demwe Power Limited.
  • Model: It was built on BOOT (Build, Own, Operate)model
  • Objective: It aims to generate 1,750 megawatts of hydroelectric power through a run-of-the-river project involving a dam and powerhouse.
  • Environmental requirements: The project involves diversion of approximately 1,416 hectares of forest land, submergence of around 1,590 hectares and the proposed felling of nearly 43,000 trees, according to the recent objections.

Major Environmental Concerns

  • The project may affect the critically endangered white-bellied heron and wildlife habitats connected with Kamlang and Namdapha.
  • Forest fragmentation could weaken wildlife corridors and ecological connectivity.
  • Mishmi and other indigenous communities have raised concerns about livelihoods, ancestral landscapes and the sacred Parashuram Kund.
  • Changes in river flow may affect downstream ecosystems and communities.

Regulatory and Legal Background

  • Environmental clearance was granted in February 2010 under the Environment Impact Assessment Notification, 2006.
  • In October 2017, the National Green Tribunal directed reconsideration of wildlife-related issues and suspended forest clearance until the required decision.
  • The Standing Committee of the National Board for Wildlife subsequently allowed construction to commence in September 2018, subject to conditions.
  • In 2026, the environmental clearance was extended until 2037, according to reports on the expert appraisal committee’s decision. The project also returned to consideration following a May 2026 agreement involving Greenko and the Arunachal Pradesh Government.

Way Forward

The controversy highlights the need for cumulative environmental impact assessment, independent wildlife studies, meaningful consultation with indigenous communities and strict compliance with forest and wildlife laws.

One-line Takeaway: The Demwe Lower project highlights the challenge of balancing renewable energy development with biodiversity conservation and the rights of indigenous communities in the Eastern Himalayas.